The requirement
A controlled manufacturing process that documented work instructions, operating parameters, dimensional and test data, and allowed customer surveillance at the Ameritube plant, all in accordance with the purchase order. The tubing had to be annealed, hydrostatic and air-underwater tested, flattening and expansion tested, and shipped with MTRs.
How the order ran
| Step | Operation |
|---|---|
| 1 | Receiving inspection and MTR review |
| 2 | Batch and heat allocation |
| 3 | Pilgering |
| 4 | Cutting |
| 5 | Drawing |
| 6 | Final annealing |
| 7 | Final inspection |
| 8 | Hydrostatic testing |
| 9 | Air underwater testing |
| 10 | Flattening, expansion, tensile, and micrographic analysis |
| 11 | Boxing and bundling for export |
Work-order control and routing gave full traceability from raw material to finished product. Operating parameters were recorded for every critical process: temperature, time, pressure, and material data. In-process monitoring, inspections, and calibrated equipment kept the tube to specification, and the customer's inspectors had open access to production, inspection, and test records.
Testing
Non-destructive: eddy current, hydrostatic, air underwater, ultrasonic, positive material identification. Destructive: flattening, expansion, tensile, microstructure and grain size, spectrometry.
The result
3,600 pieces of C71500 seamless tubing delivered in export-ready packaging, on time, with all testing complete to the ASME, ASTM, and military specifications, customer surveillance and third-party inspection satisfied, and the documentation package accepted.